Action list from JF Installation meeting - 24 january 2008 ---------------------------------------------------------- Installation Schedule : - the 15 of may the JFC1 side C shall be installed - the 23rd of may the JFC1 side A shall be installed A-frame : - final drawings for the reinforcement shall be finalised soon to start the production process (Erik) - Revision of the Feet and the interface with the JFC1 shall start. (Erik) - survey of the current A-frames (Done, 25 January) - Machining : Raphael is investigating the possibility to machine the A-frame at CERN with portable milling machines. - Produce a calculation note for SC with the final design. (Dimi) HF Truck : - Check the possibility to installed the JFC1 with the compressed truck. (Pietr) - Check the access of the truck with the surface crane (Pietr) - Check the possibility to store the HF truck on USA side during the Big Wheels movement (Pietr) Bridge-JFC1 - The installation of JFC1 requires a positioning at a level of few millimetres in X and Z direction. Such precision can not be reached with the air pad system, this is why a additional mechanism at the level of the rails of the truck shall be studied. (Jan) - The manipulation with the crane of the JFC1 requires the installation of lifting lugs. (heavy pieces, time consuming in a hot area). A quick connection would be well come. (Albert) - In function of the what Albert will find, integration of the system and possible machining will be define in the design office (to be define) - Interfaces with the A-frame and Monobloc shall be studied taking into account the positioning the JFC1. (to be defined) JFC2, JFC3, octogonal pieces - Check the access with the hook (Pietr) - Review the interfaces with the JFC1 and design some guiding system to ease the installation. Check also if quick connections with the crane can be used. (to be defined) - Fill the plane in between the shielding element. (to be defined)